You are a project manager of a manufacturing company and for you accuracy has the highest importance. In order to meet the product acceptance criteria you have to perform several activities such as measuring, examining, and verifying including reviews, audits and walkthroughs. The above scenario best describes which process?
Options:

A: Perform Quality Control

B: Validate Scope

C: Perform Quality Assurance

D: Perform Quality Assessment
sunku65
Contributor
Contributor
Posts: 259
Joined: Mon May 26, 2014 7:23 am

Re: Test question

Postby sunku65 Thu Jul 31, 2014 10:30 am

C
mandarapu
Contributor
Contributor
Posts: 176
Joined: Wed Jul 09, 2014 5:13 pm

Re: Test question

Postby mandarapu Thu Jul 31, 2014 10:52 am

thank you sunku - this guy is really confusing - he is saying it is 'validate scope' which is no way for me.
it was given accuracy is the objective and hence 'perform quality assurance' is right even for me.So better be careful with these sample test papers in 'pmpforsure' website.Any coments from any on this ?.
mandarapu
Contributor
Contributor
Posts: 176
Joined: Wed Jul 09, 2014 5:13 pm

Re: Test question

Postby mandarapu Thu Jul 31, 2014 11:03 am

Till now I had 3 to 4 questions with wrong answers - one u have just answered between C,D in another question and in 2 more question also.
sunku65
Contributor
Contributor
Posts: 259
Joined: Mon May 26, 2014 7:23 am

Re: Test question

Postby sunku65 Thu Jul 31, 2014 1:41 pm

What is the correct answer and justification from PMPforSure.
sekhar7791
Posts: 1
Joined: Wed Mar 26, 2014 8:28 am

Re: Test question

Postby sekhar7791 Thu Jul 31, 2014 2:00 pm

I feel the Answer is Validate Scope and Inspection is T&T in Validate Scope

(Inspections: measuring, examining, and verifying including reviews, audits and walkthroughs)
mandarapu
Contributor
Contributor
Posts: 176
Joined: Wed Jul 09, 2014 5:13 pm

Re: Test question

Postby mandarapu Fri Aug 01, 2014 6:51 am

Sekhar,Sunku,

The answer there is 'Validate scope'.ok Sekhar !!let us go by you that the tools and techniques of 'validate scope' matches with what given the question and asper you wrote but then why it should be said in the beginning of the question the below powerful statement.

"You are a project manager of a manufacturing company and for you accuracy has the highest importance". which means 'accuracy' mean 'measure of correctness' by definition of quality - so over all 'control quality' makes sure the deliverables are 'correct' and 'validate scope' makes it for 'acceptance'.Now please tell me - which option we choose and why ?.
mandarapu
Contributor
Contributor
Posts: 176
Joined: Wed Jul 09, 2014 5:13 pm

Re: Test question

Postby mandarapu Fri Aug 01, 2014 7:16 am

Ohh !! This question looks tricky - 'Control quality' is not given in the options at all.so 'validate scope' could be the answer. But this question is double twisted - initially saying 'accuracy' and later 'acceptance' ( objective of validate scope ) and tools of validate scope.So please comment.
mandarapu
Contributor
Contributor
Posts: 176
Joined: Wed Jul 09, 2014 5:13 pm

Re: Test question

Postby mandarapu Fri Aug 01, 2014 11:29 am

May be the question wants to point out that if one chooses validate scope - it covers through Control quality - as this process is input to validate scope. But very tricky - it is difficult to answer in such short time.
krsudeepc
Posts: 17
Joined: Wed Jul 16, 2014 12:24 pm

Re: Test question

Postby krsudeepc Fri Aug 01, 2014 12:42 pm

The question is about which process group performs - measuring, examining, and verifying including reviews, audits and walkthroughs ?
Answer is simple Validate scope.

It is important to understand the tone of question and develop answer based on it.
sunku65
Contributor
Contributor
Posts: 259
Joined: Mon May 26, 2014 7:23 am

Re: Test question

Postby sunku65 Fri Aug 01, 2014 1:11 pm

"In order to meet the product acceptance criteria you have to perform several activities...." Remember this line, this is not definitely in Control Quality.
Generally reviews, audits and walktroughs done in Executing.
nagarwal
Participant
Participant
Posts: 60
Joined: Sun Jun 22, 2014 8:34 am

Re: Test question

Postby nagarwal Mon Sep 01, 2014 6:42 am

Straight forward logic:

Validate Scope is done by the customer. Here the question is saying " You have to perform several activities such as measuring, examining, and verifying including reviews, audits and walkthroughs". The answer is clearly Quality Assurance since quality assessment and quality control are weird answers.
umeshbww
Contributor
Contributor
Posts: 168
Joined: Fri Aug 15, 2014 3:02 pm

Re: Test question

Postby umeshbww Mon Sep 01, 2014 5:20 pm

Answer is Validate Scope.
Based on practice questions so far - I have reazlied first or more sentences always included to confuse people - Asking part of Q is always defined in last sentence.