Project integration management

Postby mandarapu Tue Jul 22, 2014 12:13 pm

You are taking over a project during project planning and discover that six individuals have signed the project charter.Which of the following should be MOST concern year ?.

A.who will be a member of the change control board
B.Spending more time on configuration management
C.Getting a single project sponsor
D.Determining the reporting structure

Which is right and why ?.
sunku65
Contributor
Contributor
Posts: 259
Joined: Mon May 26, 2014 7:23 am

Re: Project integration management

Postby sunku65 Tue Jul 22, 2014 2:08 pm

C. Getting a single sponsor. because, who will provide funding.
mandarapu
Contributor
Contributor
Posts: 176
Joined: Wed Jul 09, 2014 5:13 pm

Re: Project integration management

Postby mandarapu Wed Jul 23, 2014 11:34 am

thanks....But Rita in integration management chapter end questions - says...that option of Configuration mgmt is right - I don't know how it was ?.
pankajchaturvedi245
Posts: 1
Joined: Wed Jul 02, 2014 9:49 am

Re: Project integration management

Postby pankajchaturvedi245 Tue Aug 05, 2014 11:00 am

For me the answer should be "c".
sunku65
Contributor
Contributor
Posts: 259
Joined: Mon May 26, 2014 7:23 am

Re: Project integration management

Postby sunku65 Tue Aug 05, 2014 3:52 pm

The Charter signed by Six Key stakeholders means you need to configure them in Communication management plan for what they want, when they want, how they want.
jasmeenu
Posts: 2
Joined: Fri Apr 21, 2017 12:35 pm

Re: Project integration management

Postby jasmeenu Mon Apr 24, 2017 5:47 pm

For this question...scordo book says answer is " get single sponsor"
Rita book say answer is " spending more time on configuration management.
And a website tutorialspoint say answer is " determining reporting structure"
Now its confusing as 3 sources give 3 different answers.
If anyone can please justify.
manishpn
Expert
Expert
Posts: 2333
Joined: Sat Jan 04, 2014 3:55 pm

Re: Project integration management

Postby manishpn Tue Apr 25, 2017 5:18 pm

Its very difficult one as all 3 options selected by different sources makes sense to me, however if I have to choose one I will go with option C
as Usually charter is signed by sponsor ,

yes there will be additional demands on configuration management and maybe multiple reporting lines and that is a challenge, but that is still manageable but if you have multiple sponsors then PM will have difficult time in getting additional funds, removing roadblocks during project duration etc.
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/