"The activities of product validation, updating records, performing an audit, and archiving lessons learned are all activities of ?
1. Close Project or Phase
2. Close Procurements."

As per Rita, answer is Close Procurements

Is Product validation part of Close Project or Phase? I am talking about "Product Validation" and not "Scope Validation".
signor_rk
Contributor
Contributor
Posts: 182
Joined: Wed Jun 18, 2014 3:47 pm

Re: Q1 on Closing....

Postby signor_rk Mon Jul 21, 2014 11:21 am

Though I am do not have Rita's book for reference , as per PMBOK5 , I think it should be the Option # 1 , Close Project or Phase (Ref Page# 28).
Regards ,

Ranjit
namita
Super Member
Super Member
Posts: 502
Joined: Wed Dec 11, 2013 10:25 am

Re: Q1 on Closing....

Postby namita Mon Jul 21, 2014 11:38 am

So you can clearly make its related to procurement closure by looking at work Audit

Product validation is something happens when we have outsourced the work and get a full product as buyer. So before closing all the contracts with sellers we need to have a final validation done on it in close procurments
Sud
Contributor
Contributor
Posts: 129
Joined: Sun Jun 29, 2014 4:06 am

Re: Q1 on Closing....

Postby Sud Tue Jul 22, 2014 8:44 am

Hello,

Right. Procurement Audit is a T&T of Close Procurement process. An Input to Close Project/Phase is "ACCEPTED DELIVERABLES"...

--Sud