record management system

Postby mandarapu Thu Jul 17, 2014 7:00 pm

As part of record management system,you are trying to make sure all records from the procurement are documented and indexed.Which of the following do you NOT have to worry about ?.

A.Proposal
B.Procurement SOW
C.Terms and conditions
D.Negotiation process

This is question no 17 from page 517 of Rita.In the question- NOT may not be required and correct answer is D.Please comment on this ?.
signor_rk
Contributor
Contributor
Posts: 182
Joined: Wed Jun 18, 2014 3:47 pm

Re: record management system

Postby signor_rk Fri Jul 18, 2014 3:48 am

As per PMBOK5 ref. Page#377 , the Project Manager may not be the lead negotiator on procurements. Therefore , the right answer is Option # D .
Regards ,

Ranjit
sunku65
Contributor
Contributor
Posts: 259
Joined: Mon May 26, 2014 7:23 am

Re: record management system

Postby sunku65 Fri Jul 18, 2014 5:47 am

Negotiation process is in verbal. The main focus of Negotiation process is getting fair deal and reasonable price.
mandarapu
Contributor
Contributor
Posts: 176
Joined: Wed Jul 09, 2014 5:13 pm

Re: record management system

Postby mandarapu Fri Jul 18, 2014 11:21 am

Super Signor_rk and sunku: :-) giving page no s also from PMBOK.great.thanks
Housam Bassal
Contributor
Contributor
Posts: 239
Joined: Fri Nov 04, 2016 7:38 pm

Re: record management system

Postby Housam Bassal Mon Feb 06, 2017 3:16 pm

I think the correct option is D, as negotiation process is a process and not a record, Record Management system is for index and archive the records of procurement .
Housam Bassal
Ecuador - Quito
LinkedIn: https://www.linkedin.com/in/housam-bassal-49984357