Procurement Question

Postby mandarapu Thu Jul 17, 2014 6:55 pm

A project performed under a cost -reimbursable contracthas finally entered 'close procurement'.What MUST buyer remember to do ?.

A.decrease risk rating of the project
B.Audit seller's cost submittals
C.Evaluate the fee she is paying
D.Make sure seller is not adding resources

What is right answer and why ?. Why not D cannot be right ?.
signor_rk
Contributor
Contributor
Posts: 182
Joined: Wed Jun 18, 2014 3:47 pm

Re: Procurement Question

Postby signor_rk Fri Jul 18, 2014 4:05 am

Option # B seems to be the correct answer. The Option # D is already covered in Option # B.
Regards ,

Ranjit
sunku65
Contributor
Contributor
Posts: 259
Joined: Mon May 26, 2014 7:23 am

Re: Procurement Question

Postby sunku65 Fri Jul 18, 2014 5:53 am

A project performed under a cost -reimbursable contracthas finally entered 'close procurement'.What MUST buyer remember to do ?.

A.decrease risk rating of the project
B.Audit seller's cost submittals
C.Evaluate the fee she is paying
D.Make sure seller is not adding resources

D is also comes part of the B. Here Choice B is more weight-age than D.

The Audit Seller's cost submittals additionally focus on make sure the contract won't add his other projects invoices or other buyers invoices into this project cost invoices.
namita
Super Member
Super Member
Posts: 502
Joined: Wed Dec 11, 2013 10:25 am

Re: Procurement Question

Postby namita Fri Jul 18, 2014 7:25 am

Agree with Option B as most important aspect in closing procurement is to ensure all the costings has happened correctly