Q. Your project assistant just informed you that project has 400 stakeholders in 50 countries . Project Manger has to manage 100 team members. The project has CPI=.97 and 10 weeks behind the schedule .What project manager should
focus.
1. Cost
2. Schedule
3 .Stakeholders
4. Human Resources.
Correct Answer : Option 1
The main issue is CPI though project is behind the schedule.
Can anybody explain further.
Best Regards,
Earn Value Management
- seema.sonkiya
- Expert
- Posts: 1991
- Joined: Fri Jul 11, 2014 11:57 am
Re: Earn Value Management
What is the source of the question? These type of questions does not comes in the exam.
Here CPI is less than one, this means the project is over budget.
Here CPI is less than one, this means the project is over budget.
Thanks & Kind Regards,
Seema Sonkiya, PMI-PBA Trainer
http://www.izenbridge.com/pmi-pba/online-course/
http://www.izenbridge.com | Email: seema.sonkiya@iZenBridge.com
Seema Sonkiya, PMI-PBA Trainer
http://www.izenbridge.com/pmi-pba/online-course/
http://www.izenbridge.com | Email: seema.sonkiya@iZenBridge.com
Return to “PMI-PBA Open Forum”
Who is online
Users browsing this forum: No registered users and 1 guest