Postby Rajkumar Nair Fri Nov 30, 2018 8:54 am

1.Is it possible to change the Priority During Sprint ?
2. Is it possible to Change the Story Point (Increase or Decrease) During sprint?
seema.sonkiya
Expert
Expert
Posts: 2235
Joined: Fri Jul 11, 2014 11:57 am

Re: Change During the Sprint

Postby seema.sonkiya Mon Dec 17, 2018 11:43 am

1.Is it possible to change the Priority During Sprint ?

Yes, as an exception, if business condition changes, prioritizes can be changed. PO and development team collaborate to take a call how to reorganize the existing work of sprint. For example, If a new priority item is added a low priority item can be removed.


2. Is it possible to Change the Story Point (Increase or Decrease) During sprint?


It is not changed. Story point is just an indication of effort involved. During Sprint, Stories are decomposed in tasks and ideal hours or days can be used to estimate.