When to educate stakeholders?

Postby seema.sonkiya Fri Nov 02, 2018 9:21 am

Got the following question:

At what Phase / Stage "Educating Stakeholders about Agile" is happening in Agile Environment?
and who is responsible for educating different type / level of Stakeholders ?

FOR EX > 1.Executives and proiect sponsors: Phase / Stage & Responsible Person ??
2.Managers:Phase / Stage & Responsible Person ??
3.The development team:Phase / Stage & Responsible Person ??
4.Supporting groups:Phase / Stage & Responsible Person ??
5.Third Pary Vendor : Phase / Stage & Responsible Person ??


What is the source of this question, I did not get it. Nothing like educating stakeholders, we engage them as per the needs of the project and as per stakeholders characteristics.

Engaging stakeholders is the responsibility of product owner throughput the project based on involvement needs.
For facilitation, and team development SM has the responsibility.