Chapter 7: User Stoies - question from "Life Cycle of a user story"

Postby saggarwal Thu Feb 15, 2018 1:09 am

Saket talked about a real-work scenario where PO adds more acceptance criteria to a user story during a demo. I would like to know how will this be addressed:
a) would we create a new user story with the new acceptance criterias and mark the current story Done ?
b) or we move this story to next Sprint with additional criteria added to it.
c) or any other way

Thanks
seema.sonkiya
Expert
Expert
Posts: 2052
Joined: Fri Jul 11, 2014 11:57 am

Re: Chapter 7: User Stoies - question from "Life Cycle of a user story"

Postby seema.sonkiya Thu Feb 15, 2018 5:49 am

Acceptance criteria are added to a particular user story. You can move this story to the product backlog with additional criteria added to it. Based on priority, in Sprint planning meeting, a new set of user stories will be selected