Include Project Related meetings as tasks in Sprint Backlog

Posted: Fri Dec 29, 2017 3:06 pm
by lorihewig
Hi- I'm having difficulty understanding what tasks to include in the Sprint Backlog when the tasks are not directly the results of disaggregating a user story into engineering tasks. For example, Mike Cohn recommends "identify, estimate, and include tasks for meetings related to the project." He creates a single task of say 9 hours to include planning time and time spent by each team member. However, this task doesn't have an associated product backlog item. Hence, no story points will be counted in a release burndown chart or reflected in a velocity chart, even though the Sprint burndown chart will include it. My question, is it okay to have tasks in the sprint backlog that do not connect back to a PBI? Or should we also create a PBI for those? (Mike does not state this explicitly)

Many thanks,
Lori

Re: Include Project Related meetings as tasks in Sprint Backlog

Posted: Tue Jan 02, 2018 1:27 pm
by seema.sonkiya
You can add any user story in the iteration backlog which is related to the Sprint Goal. Now task can be identified for this user story.

I advise to go through following videos: