In the below question what does "read just the release milestones" mean in the option 3 of the answer?
Question 2
1.00/0.00
The customer tells you in the middle of the release that one feature that is already in progress is no longer required. This feature is an epic and significant effort has already gone into the development. What should the team do next?
Keep going as per the current release plan – it is too late for a change in release scope.
Redirect the change request to Change Control Board. The team could address it in the next release.
Stop development on this feature right away and read just the release milestones.
Abandon the current sprint and release. The team must re-plan for the release.
Regards,
Preeti Kumar
Need help to understand question
Re: Need help to understand question
Looks like type issue.