Regarding Velocity

Postby usha1 Mon Mar 20, 2017 11:53 pm

Number of story points 31, team velocity 10 per iteration and how many iterations it takes to complete the work-Saket could you answer this question? Answer : 3 or 4?
User avatar
saket
Site Admin
Site Admin
Posts: 3077
Joined: Sat Dec 07, 2013 10:37 pm

Re: Regarding Velocity

Postby saket Tue Mar 21, 2017 3:20 am

No rule for this in general but since we are doing estimate and it make some sense to keep some contingency reserves we should say 4, since even if we do with planned velocity we will not finish it in 3 iterations.

I understand sometime this becomes tricky in PMI-ACP exam.
Explore our online PMP Program , it makes PMP Easy :-) http://goo.gl/ZmD3xF

Image Image Image Image
usha1
Posts: 3
Joined: Mon Feb 20, 2017 4:26 pm

Re: Regarding Velocity

Postby usha1 Tue Mar 21, 2017 3:06 pm

Thank you Saketh.
I remembered ,I chose 4.I was very curious to know the answer to make sure my thought was correct or not.Thank you again.