Page 1 of 1

Agile earned value management

Posted: Mon Jul 29, 2019 8:10 pm
by Kumar101
Agile earned value management is most appropriately applied at which level?


Iteration
KINDLY explain ?

Re: Agile earned value management

Posted: Tue Jul 30, 2019 10:10 am
by seema.sonkiya
Earned Value Management (EVM) is a well known project management technique which measures the integration of technical performance, cost and schedule against planned performance within a given project.

EVM is an integration of technical performance, cost and schedule against planned performance. This calculation needs following:

- The total storypoints completed
- The number of Iterations completed
- The total Actual Cost;
- The total story points added to or removed from the release plan.

So, you can do, whenever you have above information and based on your project & stakeholder's need.

Re: Agile earned value management

Posted: Tue Jul 30, 2019 10:11 am
by seema.sonkiya
Please post your questions in right thread. I am moving in ACP Queries and Tips.