Joy is creating consolidated weekly status report of his project, which of the following will not be useful input for this process?

1.Communications Management plan
2.Work performance Reports
3.List of Stakeholders
4.Government regulations

Answer - 3
Quampus Explanation - Stakeholder register is not needed as an input to manage communication, Government regulations are part of Enterprise Environmental factors which may influence the weekly report creation process.

My question - Is Stakeholder list not an input because its already a part of communication Management Plan?