RISK Management Assessment Question

Posted: Sat Jan 27, 2018 6:29 am
by brijrajpandey
Risk Mgt Q2.jpg
Risk Mgt Q2.jpg (96.15 KiB) Viewed 95 times



Why Option 4 is incorrect please justify.

Re: RISK Management Assessment Question

Posted: Sat Jan 27, 2018 7:28 am
by ajaynit
lets says risk is "ABC"

impact: 1 (low)
probability: 2 (medium)

risk score: 1*2=2

question is telling that there is dispute about this above calculation itself ,means either impact (1) or probability (2) in above question is not properly rated.


probability and impact matrix is true and should be presented only when everyone is agreeing about impact and probability assessment/rating...