Dear Folks , Please share your reasoning

You are the Project Manager for XYZ project. The scope of the project has been completed. You receive a request for a new module to be developed as part of this project. What should you do next?

a. You should approach the Project sponsor and ask her for a new module to be developed as part of this project.
b. You should approach the Senior Management and ask them for a new module to be developed as part of this project.
c. You should send the request to Change Control Board for approval.
d. Since the project scope is completed you should inform the customer that this change cannot be done as part of the project.

Re: Mock Exam Question #5 - Reasoning

Posted: Mon Dec 04, 2017 11:05 am
by pradeepbhatt13
I think it should be D

Option A and B are tempting but I think the tone of those options indicate that you are simply accepting the demands of the Customer (which are unreasonable given that the Scope has been completed) and putting the ball in Sponsor or Senior Management's court


Btw What is the source of this mock exam?

Re: Mock Exam Question #5 - Reasoning

Posted: Mon Dec 04, 2017 3:46 pm
by kushalks87
D as the scope is completed we cannot accomplish the new objective in the existing project

Re: Mock Exam Question #5 - Reasoning

Posted: Tue Dec 05, 2017 12:00 am
by Prembalaji
Yes correct answer is D