Mock Exam Question#4 - Reasoning

Posted: Sat Dec 02, 2017 5:00 am
by Prembalaji
Deear Folks , Please share your thought process

You are assigned to a new project and when you start the work, you find that the project charter has been prepared. However, nothing has been done beyond that. What will you do next?

1.Prepare a PI Matrix for Risks
2.Start the preparation of Project Management Plan
3.Track all changes through Integrated Change control
4.Get approval to prepare Project Management Plan

Re: Mock Exam Question#4 - Reasoning

Posted: Sat Dec 02, 2017 11:29 am
by suresi00
Prepare the PM plan. He is assigned to the project by the PC being approved. Now in reality the first step is to find the stakeholder and then all other planning process will get initiated.