You are leading a team to review and improve the project
selection and prioritization method. You know that the two most important questions to answer are “can we do the project?” (feasibility study) and “should we do the project?” (cost-benefit analysis). The team is considering many different management concerns, including financialreturn,
market share, and public perception. The most important criterion for building a project selection model is—

a. Risks
b. Realism
c. Ease of use
d. Benefits realization
manishpn
Expert
Expert
Posts: 2494
Joined: Sat Jan 04, 2014 3:55 pm

Re: Initiating Group Question

Postby manishpn Thu Nov 30, 2017 10:24 pm

akitut wrote:You are leading a team to review and improve the project
selection and prioritization method. You know that the two most important questions to answer are “can we do the project?” (feasibility study) and “should we do the project?” (cost-benefit analysis). The team is considering many different management concerns, including financialreturn,
market share, and public perception. The most important criterion for building a project selection model is—

a. Risks
b. Realism
c. Ease of use
d. Benefits realization



Not sure about this, all criterion are relevant not sure if there is any published ranking of these, If i had to choose I would go with realism. as the model has to be realistic with organizations goals and objectives
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/

Return to “iZenBridge PMP Open Questions”

Who is online

Users browsing this forum: No registered users and 1 guest