Ethical question

Posted: Tue Nov 21, 2017 7:57 am
by shaibajit
6789962e-8b45-46e5-a47a-6086a9f577f5.jpg
6789962e-8b45-46e5-a47a-6086a9f577f5.jpg (111.04 KiB) Viewed 391 times

Re: Ethical question

Posted: Tue Nov 21, 2017 8:58 am
by kushalks87
i think it should be 3

Re: Ethical question

Posted: Tue Nov 21, 2017 10:38 am
by rahul.kanugo
D, as PM may go for second choice of leadership person.

Doing nothing again is unethical if right candidate is not rewarded.

Giving training is not related.

Finding some other option as subcontarctor is long process. Futher, if it is a regional cultural issue .

Re: Ethical question

Posted: Tue Nov 21, 2017 12:21 pm
by suresi00
Choice A is the right answer as it is unethical to work with subcontractors who shows discrimination. I have seen this question in one of the free PMP simulator.

Re: Ethical question

Posted: Tue Nov 21, 2017 4:57 pm
by shaibajit
I also feel that option D is correct. Reason for not selecting option A is that it is the culture of that country.

Re: Ethical question

Posted: Tue Nov 21, 2017 10:40 pm
by suresi00
But why should we promote another team member? What is the rationale from your perspective? Because then you are not doing justice to your job as the requirement from project perspective is to promote top performing person.

Re: Ethical question

Posted: Wed Nov 22, 2017 8:46 am
by kushalks87
Manish Sir,

Can you please let us know the right answer to this?

Re: Ethical question

Posted: Sun Dec 03, 2017 6:23 pm
by manishpn
shaibajit wrote:6789962e-8b45-46e5-a47a-6086a9f577f5.jpg



As pr PMI, Practice of ethics may differ from culture to culture,
A situation described can be very relevant to countries in middle east or some African countries as well.

You cannot override a countries culture but have to respect that even though it may not be aligned with organizational policy ,

I would go with option #4,

Re: Ethical question

Posted: Thu Dec 07, 2017 6:18 am
by nazrulq
Same type question in Scordo answered withdrawal or cancellation of the project but as Manish said some middle eastern counties and some countries in Africa have adopted the same rule.
I think if PMI s concern to cancel the project, they should revise their answer and made it as per option 4.