Page 1 of 1

Situational Question

Posted: Tue Nov 14, 2017 10:59 am
by komal
You are project manager for website development company. Testing team finds some issues while testing the accounting module and logs in the bug tracking system. What should be your next action?
A) Inform immediately to client
B( Implements the change
C) Follow change request process
D) Do nothing as issue reported by internal QA team

Re: Situational Question

Posted: Tue Nov 14, 2017 2:23 pm
by rattaniahmed
It should be ' Option C ' because changes will be cater in Integrated Change Control Process.

Re: Situational Question

Posted: Tue Nov 14, 2017 3:26 pm
by komal
But this issue is not impacting project scope,cost and Time.

Re: Situational Question

Posted: Wed Nov 15, 2017 5:52 pm
by puja.pajan1984
Please confirm the source of this question.

Re: Situational Question

Posted: Sat Nov 18, 2017 5:39 pm
by manishpn
komal wrote:But this issue is not impacting project scope,cost and Time.

Why do you assume that CR is needed only if it impacts baseline? Do not assume. Also when in doubt try to use elimination technque
A) Inform immediately to client - This is not needed as informing client is only needed if there is some major issue

B( Implements the change - Implementation of change will happen after it is approves through ICC mechanism so this is not the next step

C) Follow change request process

D) Do nothing as issue reported by internal QA team - Doing nothing for a bug is not an option

Re: Situational Question

Posted: Mon Nov 20, 2017 4:14 am
by nazrulq
At first, PM has to analyze the impact of the change either alone or with the team before taking the further option.
Implementation of change only done after approval of CCB.But he has to log the change request either approved or rejected!