EVM question

Postby nirajsys@gmail.com Mon Oct 16, 2017 5:18 pm

You are given 10 members for 10 days to complete the project.4 days have passed and you were able to complete 30% of the work.Your team has spent 10 hours every day instead of planned 8 hours on the project.As per the plan,you should have completed 36% of the work.Calculate CPI.
1.0.6
2.0.9
3.1.2
4.1.7

My view -

I would convert all in member-hours and proceed.

BAC=10*10*8=800 member hours

EV=30%of 800=240 member hours
PV=35%*800=280 member hours

CPI=EV/AC

How do I get AC?

Pls advise.
manishpn
Expert
Expert
Posts: 2210
Joined: Sat Jan 04, 2014 3:55 pm

Re: EVM question

Postby manishpn Tue Oct 17, 2017 6:18 pm

AC = 10 hours * 10 team Member *4 Days
= 400
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist