One of the stakeholders of a project initiated a change request which was then documented in the change control system. In general, who usually would be responsible for approving or rejecting the change request?

A. An authority within the project management team or external organization.

B. The PMO

C. The stakeholder who raised the change request.

D. The project manager or Sponsor

Change request approval or rejection authority comes under CCB, when project manager raise Change request after analysis to CCB. As Project manager is raising request answer should be A but mentioned is D as correct answer. Please explain.
kushalks87
Contributor
Contributor
Posts: 102
Joined: Sat Aug 19, 2017 10:40 am

Re: Mock Test CCB

Postby kushalks87 Sun Oct 15, 2017 8:58 am

It has to be D as there is no mention of CCB. Please see the attached excerpt from PMBOK
cr.JPG
cr.JPG (88.46 KiB) Viewed 101 times