Hi ,

Please can you let me know , cost for implementing CR will be taken from contingency reserves or its an additional approved cost which will be added to cost baseline ?

Asim Ali
Posts: 19
Joined: Wed Nov 08, 2017 4:47 am

Re: Cost of change request implementation

Postby puja.pajan1984 Sat Mar 03, 2018 9:34 pm

Cost of quality is a tool and technique used in determining budget. COQ includes cost for non conformance (Defect repair/ rework etc) or conformance (preventive, corrective action), so In my opinion, it should be part of cost baseline. But if a change is implemented as part of risk response or workaround only then it can be taken from contingency reserve.