Postby KaurP Sun Aug 26, 2018 8:45 pm

Hi Manish,

Who would be involved in creation of lessons learned throughout of project lifeycyle?

A. Team members
B. Stakeholders
C. Management of performing organization
D. Project Office

People who work on a project can capture the lessons better than other stakeholders. I think its the team members who capture the lessons however they are also considered as stakeholders. So what should be the best answer for this one?

I think the same people would capture the final lessons learned in closing phase too or rest of the stakeholders are also involved in this activity at that time?

Thanks!
manishpn
Expert
Expert
Posts: 2577
Joined: Sat Jan 04, 2014 3:55 pm

Re: Lesons Learned

Postby manishpn Mon Aug 27, 2018 7:16 pm

i would go with stakeholders (any stakeholder can provide input for projects lesson learnt)
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/