Hi Manish,

Which of the following change requests can bring expected future performance of the project work in line with the project management plan?

A. Corrective action
B. Defect repair
C. Preventive action
D. Probable action


A consultant has been reviewing outputs that resulted from carrying out the Monitor and Control Risks process. She lists a number of actions that are required to bring the project into compliance with the project management plan. What are these actions called?

A. Recommended preventive actions
B. Risk register updates
C. Recommended corrective actions
D. Project management plan updates

it seems both the questions are referring to the corrective action Option A and C. Is that right?
Last edited by KaurP on Sat Aug 25, 2018 10:31 am, edited 1 time in total.
KaurP
Participant
Participant
Posts: 94
Joined: Wed Apr 04, 2018 4:08 am

Re: Corrective or preventive actions

Postby KaurP Thu Aug 23, 2018 2:54 pm

Awaiting your response.
manishpn
Expert
Expert
Posts: 2577
Joined: Sat Jan 04, 2014 3:55 pm

Re: Corrective or preventive actions

Postby manishpn Sat Aug 25, 2018 4:26 pm

KaurP wrote:Hi Manish,

we need to understand the difference between corrective and preventive action
A corrective action deals with a nonconformity/variance that has occurred, and a preventive action addresses the potential for a nonconformity/variance to occur.

Which of the following change requests can bring expected future performance of the project work in line with the project management plan?

A. Corrective action
B. Defect repair
C. Preventive action
D. Probable action

This question is describing the actin needed to bring future performance in line without mentioning about any existing deviation/defect/non conformance.
So select which one is the right answer


A consultant has been reviewing outputs that resulted from carrying out the Monitor and Control Risks process. She lists a number of actions that are required to bring the project into compliance with the project management plan. What are these actions called?

A. Recommended preventive actions
B. Risk register updates
C. Recommended corrective actions
D. Project management plan updates

this question describes about M and C process output been reviewed and based on that certain actions suggested, so select appropriate option

it seems both the questions are referring to the corrective action Option A and C. Is that right?
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
KaurP
Participant
Participant
Posts: 94
Joined: Wed Apr 04, 2018 4:08 am

Re: Corrective or preventive actions

Postby KaurP Sun Aug 26, 2018 5:46 pm

Preventive action for question 1 and recommended corrective actions for question 2nd?
manishpn
Expert
Expert
Posts: 2577
Joined: Sat Jan 04, 2014 3:55 pm

Re: Corrective or preventive actions

Postby manishpn Mon Aug 27, 2018 7:08 pm

yes thats correct
Br,
Manish P