Training to the customer was provided regarding the deliverable of the project. Project is almost finished and deliverable has been accepted. Customer wants the module or written training content, which was not included in the contract. What should you do?

A. Tell customer that as it will take time to prepare the training content, he will provide it after closing the contract.
B. Tell the customer as it was not included in the contract so you cannot provide that.
C. Ask the buyer to follow a change request to modify the contract first to get the training material.
D. Prepare the training content and provide it to the customer before closing a contract.

Please suggest which one should be picked in this case?

Thanks!
manishpn
Expert
Expert
Posts: 2574
Joined: Sat Jan 04, 2014 3:55 pm

Re: contract related

Postby manishpn Fri Aug 17, 2018 4:36 pm

KaurP wrote:Training to the customer was provided regarding the deliverable of the project. Project is almost finished and deliverable has been accepted. Customer wants the module or written training content, which was not included in the contract. What should you do?

A. Tell customer that as it will take time to prepare the training content, he will provide it after closing the contract.
B. Tell the customer as it was not included in the contract so you cannot provide that.
C. Ask the buyer to follow a change request to modify the contract first to get the training material.
D. Prepare the training content and provide it to the customer before closing a contract.

Please suggest which one should be picked in this case?

Thanks!


i can suggest but i would request to attempt and tell your understanding
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
KaurP
Participant
Participant
Posts: 94
Joined: Wed Apr 04, 2018 4:08 am

Re: contract related

Postby KaurP Fri Aug 17, 2018 5:35 pm

I will go with option D.
manishpn
Expert
Expert
Posts: 2574
Joined: Sat Jan 04, 2014 3:55 pm

Re: contract related

Postby manishpn Fri Aug 17, 2018 8:33 pm

remember that whenever a contract is involved, that contract is a legal document and any change to it has to go through a formal change.
so if a change in contract scope is requested it has to go through formal process.
option C is the right choice
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/

Return to “PMP® Queries and Tips”

Who is online

Users browsing this forum: No registered users and 8 guests