Postby KaurP Wed Aug 15, 2018 9:43 am

There were few change requests raised which resulted in corrected actions. All corrective actions must be implemented in Direct and manage project work. Which process does the effectiveness of implemented corrective actions gets evaluated:

A. Direct and manage Project Work
B. Monitor and Control Project Work
C. Executing
D. Control Quality

Control quality ensures the corrected actions are implemented correctly and fully and the effectiveness of the same gets evaluated in monitor and control project work. Is that right?
manishpn
Expert
Expert
Posts: 2509
Joined: Sat Jan 04, 2014 3:55 pm

Re: Corrective actions

Postby manishpn Wed Aug 15, 2018 3:44 pm

KaurP wrote:There were few change requests raised which resulted in corrected actions. All corrective actions must be implemented in Direct and manage project work. Which process does the effectiveness of implemented corrective actions gets evaluated:

A. Direct and manage Project Work
B. Monitor and Control Project Work
C. Executing
D. Control Quality

Control quality ensures the corrected actions are implemented correctly and fully and the effectiveness of the same gets evaluated in monitor and control project work. Is that right?


This is tricky, corrective actions are different from Defect repair, Control quality will check if the repaired deliverable meets the requirement
corrective actions are taken when the project deviates from the scope, schedule, cost or quality plan in order to bring the project performance back to the baselines.
now in which processes do we check the baseline variance?
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
KaurP
Participant
Participant
Posts: 94
Joined: Wed Apr 04, 2018 4:08 am

Re: Corrective actions

Postby KaurP Wed Aug 15, 2018 5:27 pm

Not sure if I have understood you correctly--

''....Control quality will check if the repaired deliverable meets the requirement''

You mean to say that only defect repair (approved change requests) go to Control Quality process not approved corrective and preventive actions?
manishpn
Expert
Expert
Posts: 2509
Joined: Sat Jan 04, 2014 3:55 pm

Re: Corrective actions

Postby manishpn Wed Aug 15, 2018 7:53 pm

approved CR does not necessary rectify a defective product,
corrective actions are more to bring project back on track
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
KaurP
Participant
Participant
Posts: 94
Joined: Wed Apr 04, 2018 4:08 am

Re: Corrective actions

Postby KaurP Sat Aug 18, 2018 10:50 am

We check the baseline variance in almost all the M&C processes.
Controlling requires evaluating WPD again Project Mgmt. Plan and taking action to control the variance.

Will Control Quality or Monitor and Control Project Work be an answer to the give question?
manishpn
Expert
Expert
Posts: 2509
Joined: Sat Jan 04, 2014 3:55 pm

Re: Corrective actions

Postby manishpn Sat Aug 25, 2018 3:45 pm

KaurP wrote:We check the baseline variance in almost all the M&C processes.
Controlling requires evaluating WPD again Project Mgmt. Plan and taking action to control the variance.

Will Control Quality or Monitor and Control Project Work be an answer to the give question?


we discussed in the clarification session, we do evaluate individual Knowledge areas in their respective M and C process, however the question does not mention any specific KA, so we should consider overall project and not individual KA,

the answer and Monitor and control project work,
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/

Return to “PMP® Queries and Tips”

Who is online

Users browsing this forum: No registered users and 7 guests