Stakeholder Engagement Plan-Quampus Q correction

Postby KaurP Sun Aug 12, 2018 10:17 am

Question 27

The stakeholder engagement plan is a component of the project management plan and identifies the management strategies required to effectively engage stakeholders, which of the following information is expected to be available in Stakeholder Engagement Plan?

Organizational Position of Stakeholders

Major requirements

Scope and impact of change to stakeholders

Stakeholder classification Marked as correct


The question is about “Plan Stakeholder Engagement” process. PMBOK 13.2

Scope and impact of the change to stakeholders are documented in Stakeholder Engagement Plan; other options are listing the characteristic of Stakeholder Register.