Stakeholder Engagement

Postby KaurP Fri Aug 10, 2018 5:16 pm

Please help me with the answer-

Jane is managing an office refurbishment project. All of the project stakeholders have been identified and classified. The stakeholder management plan has also been approved. Jane is managing a project for the first time in her life and she is relying on the PMBOK guide as a reference to deliver a great project.

Which of the following processes would provide guidance to Jane regarding how to execute the approved stakeholder management plan?

A. Monitor Stakeholder Engagement
B. Manage Stakeholder Engagement
C. Identify Stakeholders
D. Plan Stakeholder Engagement

All subsidiary plans provide guidance on how to execute the rest of the processes of respective KA's.
Will the answer by Plan Stakeholder Engagement or Manage Stakeholder Engagement in this case?

Thanks!
manishpn
Expert
Expert
Posts: 2509
Joined: Sat Jan 04, 2014 3:55 pm

Re: Stakeholder Engagement

Postby manishpn Sat Aug 11, 2018 2:13 pm

KaurP wrote:Please help me with the answer-

Jane is managing an office refurbishment project. All of the project stakeholders have been identified and classified. The stakeholder management plan has also been approved. Jane is managing a project for the first time in her life and she is relying on the PMBOK guide as a reference to deliver a great project.

Which of the following processes would provide guidance to Jane regarding how to execute the approved stakeholder management plan?

A. Monitor Stakeholder Engagement
B. Manage Stakeholder Engagement
C. Identify Stakeholders
D. Plan Stakeholder Engagement

All subsidiary plans provide guidance on how to execute the rest of the processes of respective KA's. yes true, but the question focuses on stakeholders, and for PMP keep it simple, do not over engineer, so keeping other KAs aside answer would be manage stakeholder , actually the question is not framed well, if PM wants guidance on how execute stakeholder management/engagement, its the stakeholder management plan she should refer to, not the process itself but the document which is created as part of the process and actual management is done in manage stakeholder engagement process
Will the answer by Plan Stakeholder Engagement or Manage Stakeholder Engagement in this case?

Thanks!
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/