Lessons learned

Exclusive forum for iZenBirdge PMP® clients
KaurP
Participant
Participant
Posts: 94
Joined: Wed Apr 04, 2018 4:08 am

Lessons learned

Postby KaurP Thu Aug 09, 2018 1:28 pm

Due to a tight project schedule, a project manager did not document lessons learned all through the project. However, at the end of the project, he finally documented the lessons learned. Your comment on this would be:

A. This is ok. At a minimum, lessons learned should be documented at the end of the project.
B. This is not ok. Lessons learned must be documented all through the project as well as at the end of the project.
C. This is not ok. Lessons learned need to be documented all through the project and must not be done at the end of the project.
D. This is correct. Lessons learned are intended to be documented only at the end of the project.

Answer-
A. This is ok. At a minimum, lessons learned should be documented at the end of the project.

Shouldn't they be documented throughout the project as well as at the end?

Questions on the exam can be tricky so trying to seek clarification as much as I can.
manishpn
Expert
Expert
Posts: 2509
Joined: Sat Jan 04, 2014 3:55 pm

Re: Lessons learned

Postby manishpn Sat Aug 11, 2018 2:25 pm

KaurP wrote:Due to a tight project schedule, a project manager did not document lessons learned all through the project. However, at the end of the project, he finally documented the lessons learned. Your comment on this would be:

A. This is ok. At a minimum, lessons learned should be documented at the end of the project.
B. This is not ok. Lessons learned must be documented all through the project as well as at the end of the project.
C. This is not ok. Lessons learned need to be documented all through the project and must not be done at the end of the project.
D. This is correct. Lessons learned are intended to be documented only at the end of the project.

Answer-
A. This is ok. At a minimum, lessons learned should be documented at the end of the project.

Shouldn't they be documented throughout the project as well as at the end?

Questions on the exam can be tricky so trying to seek clarification as much as I can.


as per PMP exam outline lessons learnt is in each process group, so this questions seems like based on old exam outline content,
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/

Return to “PMP® Queries and Tips”

Who is online

Users browsing this forum: Google [Bot] and 6 guests