Which of the following is NOT an input to the process Manage stakeholder engagements?

Stakeholder Management Plan
Communication Management Plan
Change Log
Issue Log

Explanation:
An issue log is the output of the process Manage stakeholder engagements. All the other options are inputs to the process.
----------------------------------------------

Issue log (output of Direct and Manage Project Work) is one of the documents that serve as an input to Manage Stakeholder Engagement process.

Can you please check and explain this answer.

Thanks!
manishpn
Expert
Expert
Posts: 2509
Joined: Sat Jan 04, 2014 3:55 pm

Re: Stakeholder Mgmt

Postby manishpn Sun Jul 29, 2018 6:25 pm

you are correct, is this izenbridge question then it has to be rectified
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/

Return to “PMP® Queries and Tips”

Who is online

Users browsing this forum: No registered users and 4 guests