You are using control charts to perform quality control. Which of these situations does not indicate that the process is out of control and an assignable cause needs to be assigned. Assume that the control limits have been set to three sigma.

One of the point is more than the mean + (3*sigma)

Two points together are more than mean +(2*sigma), but less than mean + (3*sigma)

Seven points together are on one side of the mean.

Three points are on one side of the mean

CORRECT: b. The other two are conditions that indicate the process is out of control.

What does 'Three points are on one side of the mean' mean?
In case of Rule of Seven, there are 7 points on one side of mean. Does this mean if any points lesser than that on either side of mean also shows project is ' out of control'

Thanks!
manishpn
Expert
Expert
Posts: 2571
Joined: Sat Jan 04, 2014 3:55 pm

Re: Control charts

Postby manishpn Sat Jun 23, 2018 2:43 pm

such complicated level of questions are not normal

however if you are interested more then refer to

https://www.spcforexcel.com/knowledge/c ... rpretation

the question is describing Rule #2 mentioned in the link above
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/

Return to “PMP® Queries and Tips”

Who is online

Users browsing this forum: No registered users and 5 guests