Network Diagram

Postby KaurP Tue Jun 19, 2018 9:34 am

A Project Manager is using AOA to perform critical path analysis. The network diagram is represented as shown using below. Which of the following represents the path:
ABIR
CDHR
CDGIR
EFGIR

Activity Duration Dependent on
A 3 none
C 3 none
B 2 A
D 5 C
E 2 none
F 4 E
G 3 D,F
H 1 D,F
I 2 B,G
R 0 H,I

Both activities G and H are followed by D and F
Can this happen? Two activities having same two predecessors?

Thanks!
manishpn
Expert
Expert
Posts: 2423
Joined: Sat Jan 04, 2014 3:55 pm

Re: Network Diagram

Postby manishpn Sat Jun 23, 2018 1:15 pm

We always recommend that you draw your own SND based on the information provided and upload the image , we can discuss it later.
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/

Return to “PMP® Queries and Tips”

Who is online

Users browsing this forum: No registered users and 2 guests