When to take Change Request to CCB?

Postby pmpstudent Tue Dec 10, 2013 4:21 pm

When a change request is made by a stakeholder, a PM first files a formal change request or study the impact of the request first and then put it up to CCB? Filing a formal request and putting up to CCB mean the same?
User avatar
saket
Site Admin
Site Admin
Posts: 3113
Joined: Sat Dec 07, 2013 10:37 pm

Re: When to take Change Request to CCB?

Postby saket Tue Dec 10, 2013 4:29 pm

When a stakeholder requests a change request the first thing the PM has to do is LOG it. After logging the CR next step is doing impact analysis . Once impact analysis is done and Change Request has all information include which can help CCB to make the desired decision , this CR goes to CCB.
Explore our online PMP Program , it makes PMP Easy :-) http://goo.gl/ZmD3xF

Image Image Image Image

Return to “PMP® Queries and Tips”

Who is online

Users browsing this forum: Google [Bot] and 8 guests