Question on Schedule management

Postby kshitij_y Sun Jan 05, 2014 6:40 pm

Ref. Question in Screenshort
Is Compression of schedule is mandatory before Finalizing the schedule ?
Attachments
Question on Schedule management.png
Question on Schedule management.png (26.94 KiB) Viewed 851 times
namita
Super Member
Super Member
Posts: 502
Joined: Wed Dec 11, 2013 10:25 am

Re: Question on Schedule management

Postby namita Mon Jan 06, 2014 7:54 am

This one is little tricky. First, while answering questions, what you need to keep in mind is you have to choose the Best option among the available options. In this question:

Option A is done in define activity process which is already done before Estimate activity duration process
Option B is also done under create WBS under scope management KA
Option C is no referring to any process. We don't have any process to finalize schedule rather if it would have been develop schedule this would have been best option
Option D schedule compression is one of the T&T we use in Develop schedule process which follows estimate activity duration process. Therefore in this scenario this is the best answer. This is not mandatory to use compression however if project need crashing and fast tracking to be done this will be used.

Hope its clear :)
kshitij_y
PMP
Posts: 229
Joined: Wed Dec 11, 2013 9:39 am

Re: Question on Schedule management

Postby kshitij_y Mon Jan 06, 2014 9:12 am

Thanks Namita