Network Diagram question

Postby Venkat Sun Jun 08, 2014 9:14 pm

Hi Saket,

in the attached there are network diagrams to calculate the relationships using precedence diagramming.

I'm getting ES = '8' for activity E, but it seems to be wrong.

Could you please clarify this?

Thanks a lot,
Venkat
Attachments
1.08-06-2014 22-57-37.png
1.08-06-2014 22-57-37.png (50.36 KiB) Viewed 2143 times
namita
Super Member
Super Member
Posts: 502
Joined: Wed Dec 11, 2013 10:25 am

Re: Network Diagram question

Postby namita Mon Jun 09, 2014 2:59 am

I think ES 8 is fine for E. Is there any other dependency?
Venkat
Contributor
Contributor
Posts: 126
Joined: Sun Mar 23, 2014 6:18 pm

Re: Network Diagram question

Postby Venkat Mon Jun 09, 2014 7:25 am

thanks, i recalulated today morning and got the answer as '8' and learnt never calulate critical path at midnight. ;)
indusharma
Super Member
Super Member
Posts: 349
Joined: Wed Dec 11, 2013 2:55 am

Re: Network Diagram question

Postby indusharma Mon Jun 09, 2014 7:29 am

Venkat ,

We will look into this quampus question :)

Regards
Indu Sharma
PMP Trainer
iZenbridge Consultancy Pvt Ltd
User avatar
saket
Site Admin
Site Admin
Posts: 3125
Joined: Sat Dec 07, 2013 10:37 pm

Re: Network Diagram question

Postby saket Mon Jun 09, 2014 8:07 am

Yes friends, you are doing great in calculating it

CPM3.jpg
Critical Path with FF
CPM3.jpg (27.97 KiB) Viewed 2116 times


one more question, which activity has free float and what is the duration of that float ?
Explore our online PMP Program , it makes PMP Easy :-) http://goo.gl/ZmD3xF

Image Image Image Image
namita
Super Member
Super Member
Posts: 502
Joined: Wed Dec 11, 2013 10:25 am

Re: Network Diagram question

Postby namita Mon Jun 09, 2014 8:49 am

I shall wait for sometime for some answers... before I do :)
harin4627
Participant
Participant
Posts: 92
Joined: Thu May 29, 2014 6:50 pm

Re: Network Diagram question

Postby harin4627 Mon Jun 09, 2014 2:53 pm

Activity "c" has one day free float
indusharma
Super Member
Super Member
Posts: 349
Joined: Wed Dec 11, 2013 2:55 am

Re: Network Diagram question

Postby indusharma Mon Jun 09, 2014 4:30 pm

Activity C is the only activity which is not on Critical path.
EF for C is 6, and LF is 7 (as if E need to start on 8th day, C can start as late as 7th day).

C has 1 day as free float
Indu Sharma
PMP Trainer
iZenbridge Consultancy Pvt Ltd
namita
Super Member
Super Member
Posts: 502
Joined: Wed Dec 11, 2013 10:25 am

Re: Network Diagram question

Postby namita Tue Jun 10, 2014 5:21 am

Answer is correct. Just to elaborate on things we need to consider when we are talking about Free Float. Before anything else what is Free Float once again

The amount of time that a schedule activity can be delayed without delaying the early start date of any successor or violating a schedule constraint


So the important points when we think about Free Float are:

1. Is there more than one successor for the activity we are calculating the free float? If so, all successors ES should not be impacted. In current example this situation is not a problem as C has only one successor

2. Formula should be considering Start of successor activity/ies and finish of current activity

3. Free float can only come into existence if successor is having more than one activities converging on it or the successor activity is having constraint applied on it e.g. can not start before a defined date etc.... In our example E is having C and F so this condition is satisfying

So this is all about Free Float I have.. Anyone has anything more..please share
Last edited by namita on Tue Jun 10, 2014 6:11 am, edited 2 times in total.
indusharma
Super Member
Super Member
Posts: 349
Joined: Wed Dec 11, 2013 2:55 am

Re: Network Diagram question

Postby indusharma Tue Jun 10, 2014 5:58 am

Well explained Namita :D
Indu Sharma
PMP Trainer
iZenbridge Consultancy Pvt Ltd
kripakrish
Beginner
Beginner
Posts: 41
Joined: Wed Apr 09, 2014 2:59 pm

Re: Network Diagram question

Postby kripakrish Tue Jun 10, 2014 9:51 am

In this diagram isnt cp =27 ?ABFEG=3+4+6+4=10=27? doesnt LF of G should be 27?or not necessary always.
For back ward pass would we start with LF of G as 21 or 27?
namita
Super Member
Super Member
Posts: 502
Joined: Wed Dec 11, 2013 10:25 am

Re: Network Diagram question

Postby namita Tue Jun 10, 2014 10:42 am

As we have dependencies, CP length will be 21 in this case. Also LF will be 21 only
Housam Bassal
Contributor
Contributor
Posts: 239
Joined: Fri Nov 04, 2016 7:38 pm

Re: Network Diagram question

Postby Housam Bassal Thu Dec 22, 2016 12:13 am

saket wrote:Yes friends, you are doing great in calculating it

CPM3.jpg

one more question, which activity has free float and what is the duration of that float ?


Saket,

I have question regarding the ES of activity E

If I calculate ES of activity E depending on EF of activity C it will be 6+1=7, however If I go by the calculation ES= EF-duration+1 = 11-4+1=8

What did you choose 8 and not 7 , is there any rule for that (for example as its ES , so we need to choose the Biggest number(forward method), and in case of EF we need to choose the smallest number(backward method)?)

Please clarify?
Housam Bassal
Ecuador - Quito
LinkedIn: https://www.linkedin.com/in/housam-bassal-49984357
manishpn
Expert
Expert
Posts: 2202
Joined: Sat Jan 04, 2014 3:55 pm

Re: Network Diagram question

Postby manishpn Mon Dec 26, 2016 12:15 pm

Housam Bassal wrote:
saket wrote:Yes friends, you are doing great in calculating it

CPM3.jpg

one more question, which activity has free float and what is the duration of that float ?


Saket,

I have question regarding the ES of activity E

If I calculate ES of activity E depending on EF of activity C it will be 6+1=7, however If I go by the calculation ES= EF-duration+1 = 11-4+1=8

What did you choose 8 and not 7 , is there any rule for that (for example as its ES , so we need to choose the Biggest number(forward method), and in case of EF we need to choose the smallest number(backward method)?)
[b][i]Calculations are shown by Saket, you need to consider FF relationship and not relation between C and E[/i][/b]

harin4627 wrote:Activity "c" has one day free float

Please clarify?
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/