General query

Postby KaurP Tue May 08, 2018 8:18 am

Input like ‘Enterprise environmental factor’ and T&T ‘Meetings’ have not been mentioned in the PMBOK for Implement risk response.Similarly, ‘Expert Judgement’ is not specifically mentioned in PMBOK 6 as T&T for Monitor Risk ITTO. We heard Saket mentioning in videos that EEF will be always there..meetings is also needed for every process which we agree.
Question is should we stick to options whatever is written in PMBOK for respective processes or should answer the questions thinking that OPA & EEF (Inputs), Expert Judgement & meetings (T&T) will always be there in all the processes in the exam?

Thanks!
seema.sonkiya
Expert
Expert
Posts: 2113
Joined: Fri Jul 11, 2014 11:57 am

Re: General query

Postby seema.sonkiya Wed May 09, 2018 5:21 am

As a paid customer, please post your questions in exclusive area. I am moving there
KaurP
Participant
Participant
Posts: 94
Joined: Wed Apr 04, 2018 4:08 am

Re: General query

Postby KaurP Sat May 12, 2018 12:11 pm

Awaiting response to my query.

Thanks!
manishpn
Expert
Expert
Posts: 2539
Joined: Sat Jan 04, 2014 3:55 pm

Re: General query

Postby manishpn Sat May 12, 2018 4:22 pm

KaurP wrote:Input like ‘Enterprise environmental factor’ and T&T ‘Meetings’ have not been mentioned in the PMBOK for Implement risk response.Similarly, ‘Expert Judgement’ is not specifically mentioned in PMBOK 6 as T&T for Monitor Risk ITTO. We heard Saket mentioning in videos that EEF will be always there..meetings is also needed for every process which we agree.
Question is should we stick to options whatever is written in PMBOK for respective processes or should answer the questions thinking that OPA & EEF (Inputs), Expert Judgement & meetings (T&T) will always be there in all the processes in the exam?

PMBOK is a framework/guidelines and is not a rule book, so if a given process does not have an input which a PM think should be there, that has to be factored in tailoring options,
So when you prepare for Exam, do not stress yourself a lot if you think one of the inputs or T and T is missing in a process in PMBOK, rather focus and channel your energy in getting a logical grip on the process , rest wil follow
Exam does not ask you to memorize any ITTO


Thanks!
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/