Planning Process

Postby KaurP Tue May 08, 2018 7:49 am

Hi there,

Please help me understand how come 'Change Request' is the output of below mentioned Planning Process Group processes -

Define Activities
Develop Schedule
Plan Risk Responses
Plan Procurement Mgmt.

Thanks!
seema.sonkiya
Expert
Expert
Posts: 2104
Joined: Fri Jul 11, 2014 11:57 am

Re: Planning Process

Postby seema.sonkiya Wed May 09, 2018 5:24 am

Please post in exclusive area. I am moving there.
KaurP
Participant
Participant
Posts: 94
Joined: Wed Apr 04, 2018 4:08 am

Re: Planning Process

Postby KaurP Sat May 12, 2018 12:13 pm

Awaiting your response.

Thanks!
manishpn
Expert
Expert
Posts: 2509
Joined: Sat Jan 04, 2014 3:55 pm

Re: Planning Process

Postby manishpn Sat May 12, 2018 4:39 pm

KaurP wrote:Hi there,

Please help me understand how come 'Change Request' is the output of below mentioned Planning Process Group processes -

Define Activities
Develop Schedule
Plan Risk Responses
Plan Procurement Mgmt.

Thanks!


When you look at any process in PMBOK, you need to understand and appreciate that these processes are not only done once in the project life cycle, especially the planning processes are not only done once to baseline PMP but most of them are repeated multiple times.

Define Activities - This process helps you break down the Work Packages , however for all practical purposes for large projects where rolling wave planning is done, this process is performed as and when the WP are taken up to define activities needed to deliver them, In rolling wave planning we sometimes take a ballpark, ROm estimates for WP which are not decomposed, and when they are decomposed new risks may appear, the estimation done may not be sufficient etc and such situations may impact Project Baselines and that needs a CR
Develop schedule: a lot of T and T that are used to compress schedule may need additional resources, resulting in cost impact, some decisions may also need change in resource management plan etc

Plan risk responses:
when project plans for risk responses, there is need of additional resources, potential impact on schedule and also need to for reserve, this needs CR

Plan procurement management:
When you decide to procure the goods or services, then there will a change in project baseline as well as many subsidiary plans ,
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/