WORK PERFORMANCE DATA

Posted: Wed May 28, 2014 6:27 am
by M L Dahima
The official answer of the question is A (SCARDO)
In the situation given,team has calculated performance measurement - EV,CPI,ETC,TCPI,
Can the correct answer be C in place of A.
request clarification

Re: WORK PERFORMANCE DATA

Posted: Wed May 28, 2014 7:17 am
by saket
I will go with C since its a processed information.

Re: WORK PERFORMANCE DATA

Posted: Fri Aug 15, 2014 9:31 pm
by umeshbww
I will choose option C because TCPI is WPI (not WPD)

Re: WORK PERFORMANCE DATA

Posted: Fri Sep 05, 2014 5:14 am
by pank_pmp
"C" It is for me! Since Stakeholders do not have any idea of EVM. WPI gives them brief status of project!