WORK PERFORMANCE DATA

Postby M L Dahima Wed May 28, 2014 6:27 am

The official answer of the question is A (SCARDO)
In the situation given,team has calculated performance measurement - EV,CPI,ETC,TCPI,
Can the correct answer be C in place of A.
request clarification
Attachments
Untitled.jpg
Untitled.jpg (80.81 KiB) Viewed 1109 times
User avatar
saket
Site Admin
Site Admin
Posts: 3125
Joined: Sat Dec 07, 2013 10:37 pm

Re: WORK PERFORMANCE DATA

Postby saket Wed May 28, 2014 7:17 am

I will go with C since its a processed information.
Explore our online PMP Program , it makes PMP Easy :-) http://goo.gl/ZmD3xF

Image Image Image Image
umeshbww
Contributor
Contributor
Posts: 168
Joined: Fri Aug 15, 2014 3:02 pm

Re: WORK PERFORMANCE DATA

Postby umeshbww Fri Aug 15, 2014 9:31 pm

I will choose option C because TCPI is WPI (not WPD)
GOAL : PMP Certified by 24th Sept 2014 -- ACCOMPLISHED
pank_pmp
Super Member
Super Member
Posts: 490
Joined: Tue Aug 05, 2014 11:04 am

Re: WORK PERFORMANCE DATA

Postby pank_pmp Fri Sep 05, 2014 5:14 am

"C" It is for me! Since Stakeholders do not have any idea of EVM. WPI gives them brief status of project!