Page 1 of 1

Earned Value

Posted: Wed Feb 14, 2018 6:31 am
by satya.srinivas
Jay is managing a project which is planned to be taking effort of 1200 hours and will cost $150 per hour. When the project is completed, it had taken 1400 hours of efforts with the cost of $200 per hour. Calculate CPI and SPI.

How Earned Value and Planned Value are same in this scenario?

Re: Earned Value

Posted: Wed Feb 14, 2018 4:56 pm
by manishpn
when project is completed, SPI is always 1 , so EV and PV is always same at the end of the project

Re: Earned Value

Posted: Thu Feb 15, 2018 4:58 am
by seema.sonkiya
As a customer of iZenBridge, Srinivas please post your questions in PMP exclusive forum:

There are three sections:
PMP® Queries and Tips
PMP® Exam Prep Questions
PMP® Exclusive Webinars

Please use above sections for discussion. I am moving your thread.