Earned Value

Postby satya.srinivas Wed Feb 14, 2018 6:31 am

Jay is managing a project which is planned to be taking effort of 1200 hours and will cost $150 per hour. When the project is completed, it had taken 1400 hours of efforts with the cost of $200 per hour. Calculate CPI and SPI.

How Earned Value and Planned Value are same in this scenario?
manishpn
Expert
Expert
Posts: 2509
Joined: Sat Jan 04, 2014 3:55 pm

Re: Earned Value

Postby manishpn Wed Feb 14, 2018 4:56 pm

when project is completed, SPI is always 1 , so EV and PV is always same at the end of the project
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
seema.sonkiya
Expert
Expert
Posts: 2104
Joined: Fri Jul 11, 2014 11:57 am

Re: Earned Value

Postby seema.sonkiya Thu Feb 15, 2018 4:58 am

As a customer of iZenBridge, Srinivas please post your questions in PMP exclusive forum:

There are three sections:
PMP® Queries and Tips
PMP® Exam Prep Questions
PMP® Exclusive Webinars

Please use above sections for discussion. I am moving your thread.

Return to “PMP® Queries and Tips”

Who is online

Users browsing this forum: No registered users and 9 guests