Justin is performing actions such as reporting and comparing actual results against project management plan, analyzing performance data and determining if corrective or preventive action should be recommended, documenting all information, gathering and recording project information and monitoring approved change requests. Which process are you performing?
Aren't we monitoring the validated changes here? Approved changes are being analyzed /validated in Control Quality?
Izenbridge ( dynamic) Question on change control
Re: Izenbridge ( dynamic) Question on change control
need to know full question before i comment
have asked admin to share
have asked admin to share
Re: Izenbridge ( dynamic) Question on change control
we do not monitor approved changes in control quality
thanks for pointing that out needs to be rectified
thanks for pointing that out needs to be rectified