Closing procedure

Posted: Fri Dec 15, 2017 11:20 pm
by suresi00
Manish sir,

Can you give me the step by step procedure for closing the procedure. I see questions on what comes first.

Re: Closing procedure

Posted: Sat Dec 16, 2017 4:34 pm
by manishpn
suresi00 wrote:Manish sir,

Can you give me the step by step procedure for closing the procedure. I see questions on what comes first.


I have mentioned this quiet a few times on clarification sessions and also on forum that there is no prescribed sequence in close project phase.
we will have to use common sense based on the situation given in the question.

kindly post the question that you have confusion and i can help

Re: Closing procedure

Posted: Sat Dec 16, 2017 4:42 pm
by suresi00
One question

A project manager is in the final closure phase of the project. Which of the following should he do first as part of the project closure activity?

A. Get formal sign off from the customer to confirm customer acceptance of final deliverable
B. Measure customer satisfaction as a key performance indicator of project's success
C. Hand over the completed project deliverables to operations and management D.
D. Measure completed work (deliverables) against the scope statement