Manish sir,
Can you give me the step by step procedure for closing the procedure. I see questions on what comes first.
Closing procedure
Re: Closing procedure
suresi00 wrote:Manish sir,
Can you give me the step by step procedure for closing the procedure. I see questions on what comes first.
I have mentioned this quiet a few times on clarification sessions and also on forum that there is no prescribed sequence in close project phase.
we will have to use common sense based on the situation given in the question.
kindly post the question that you have confusion and i can help
Re: Closing procedure
One question
A project manager is in the final closure phase of the project. Which of the following should he do first as part of the project closure activity?
A. Get formal sign off from the customer to confirm customer acceptance of final deliverable
B. Measure customer satisfaction as a key performance indicator of project's success
C. Hand over the completed project deliverables to operations and management D.
D. Measure completed work (deliverables) against the scope statement
A project manager is in the final closure phase of the project. Which of the following should he do first as part of the project closure activity?
A. Get formal sign off from the customer to confirm customer acceptance of final deliverable
B. Measure customer satisfaction as a key performance indicator of project's success
C. Hand over the completed project deliverables to operations and management D.
D. Measure completed work (deliverables) against the scope statement