The project manager and a functional manager cannot reach agreement about the assignment of resources for a project. The functional manager insists that the resources are not available due to other priorities. In this case the conflict will require the assistance of the___________ to reach a solution.

a) Customer b) Project Sponsor c) Senior Manager d) Contractor

Manish sir is it sponsor or senior manager?

Re: Whom to contact for resource

Posted: Sat Dec 16, 2017 4:46 pm
by manishpn
this looks like balanced matrix example,
project sponsor there is no need for senior manager