Whom to contact for resource

Postby suresi00 Fri Dec 15, 2017 6:51 pm

The project manager and a functional manager cannot reach agreement about the assignment of resources for a project. The functional manager insists that the resources are not available due to other priorities. In this case the conflict will require the assistance of the___________ to reach a solution.

a) Customer b) Project Sponsor c) Senior Manager d) Contractor

Manish sir is it sponsor or senior manager?
manishpn
Expert
Expert
Posts: 2553
Joined: Sat Jan 04, 2014 3:55 pm

Re: Whom to contact for resource

Postby manishpn Sat Dec 16, 2017 4:46 pm

this looks like balanced matrix example,
project sponsor there is no need for senior manager
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/