WBS

Postby suresi00 Fri Dec 15, 2017 5:25 pm

The _____________ aids in creating a more detailed definition of the scope of the project and can be used to validate the work of the project.

a) Scope baseline b) Work breakdown structure c) Project charter d) Alternatives identification

Manish sir,

I wrote the answer as Scope baseline, thinking that I need to check the work with scope statement to ensure what all is included which in turn has the WBS. The answer given was WBS.

Any thoughts?
manishpn
Expert
Expert
Posts: 2509
Joined: Sat Jan 04, 2014 3:55 pm

Re: WBS

Postby manishpn Sat Dec 16, 2017 5:04 pm

suresi00 wrote:The _____________ aids in creating a more detailed definition of the scope of the project and can be used to validate the work of the project.

a) Scope baseline b) Work breakdown structure c) Project charter d) Alternatives identification

Manish sir,

I wrote the answer as Scope baseline, thinking that I need to check the work with scope statement to ensure what all is included which in turn has the WBS. The answer given was WBS.

Any thoughts?


while scope statement and WBS both are used as inputs for scope validation, WBS helps in detailing the scope
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/