You and your project team have completed your risk register, including planned responses to identified risks. What is your next step?
A: Update the work breakdown structure
. B: Begin the Control Risks process.
C: Perform another iteration of the risk register.
D: Update your project sponsor on the planned risk responses.

I couldn't answer this one correctly , I thought next in line is control risk process.

As we are still in planning process we can update WBS . Somehow missed it. thought of sharing