Change Control

Posted: Thu Dec 14, 2017 6:52 pm
by suresi00
Your client has requested a change to the project and as a result you are preparing a change request according to the approved change control process that your project management methodology prescribes. A project administrator on your project asks to assist in the preparation and assessment of the change request but seems confused about the key characteristics of a change request. You explain that all of the following are characteristics of a change request except? A: Every documented change request must be approved or rejected.
B: All change requests should be considered by the change control board.
C: They may be initiated verbally.
D: They may involve assessing impacts on several knowledge areas.

Manish sir, is it necessary for all change request to go through CCB? My understanding is yes. But want to make sure.

Re: Change Control

Posted: Thu Dec 14, 2017 8:22 pm
by manishpn
suresi00 wrote:Your client has requested a change to the project and as a result you are preparing a change request according to the approved change control process that your project management methodology prescribes. A project administrator on your project asks to assist in the preparation and assessment of the change request but seems confused about the key characteristics of a change request. You explain that all of the following are characteristics of a change request except? A: Every documented change request must be approved or rejected.
B: All change requests should be considered by the change control board.
C: They may be initiated verbally.
D: They may involve assessing impacts on several knowledge areas.

Manish sir, is it necessary for all change request to go through CCB? My understanding is yes. But want to make sure.


No , some changes can be approved by PM, the authority of PM wrt Change requests is clearly defined in PMP